WEBCAM PLANT SCHLÜSSELFELD


Get an idea of the construction progress via our live webcam:
Webcam Plant Schlüsselfeld – updated every 60 seconds

Webcam Plant Schlüsselfeld – updated every 60 seconds

CONSTRUCTION OF THE THIRD PORAVER® SITE BEGINS

LOCATION SCHLÜSSELFELD


With the construction of the third Poraver® plant, we are creating the foundation for further company growth in the coming decades. In the final stage with 8 production lines, an annual production capacity of 240,000 m³ Poraver® is achieved on the 53,000 m² new site. As a result, the company's total production capacity at its locations in Postbauer-Heng, Innisfil (Canada) and Schlüsselfeld will be 500,000 m³ per year.
The new plant in the immediate vicinity of the head office in Schlüsselfeld will consolidate and secure the company's market leadership position as the world's largest manufacturer of expanded glass in the long term.
Scheduling of construction work:
2017: Ground and leveling works (Completed)
2018: Underground works (Start in spring 2018 and construction of the access road)
2019: Construction of the production hall
2020: Installation of technical equipment and commissioning
For the new plant 40 additional employees will be hired for production and logistics. In the long term, more than 120 employees will be employed at the new Schlüsselfeld production site.